Hi,
We run tests automatically via Jenkins. Sometimes though, the build fails because 1 or more of the load generators are unavailable (being used by other tests). Is it possible to not tie the load generators to a scenario? Can the project have a pool of LGs, then check for x available LGs to use before each execution?
I've seen posts about changing the setting to x% of failed LGs for the scenario to proceed. On the other hand, that will make me need to select quite a lot of LGs and might hog the LG reservation of other tests.
Have you looked at Neoload web, when a test is run from Neoload web, the LGs are chosen dynamically based on what ones are available. Jenkins can call Neoload web