Can I add/remove virtual users during a load test or should I stop it?

I set up a load policy but I would like to adjust it depending on how my application behaves. And, I don't want to stop the test and waste time. Is it possible?

Nouredine A.
Nouredine A.

Nouredine A.

Level
4
5000 / 5000
points
Team
Nouredine A.
Nouredine A.

Nouredine A.

Level
4
5000 / 5000
points
Team

Since NeoLoad 4.0, the load policy can be modified on the fly for populations that are currently running.

You can select one of your population and decide to increase or decrease the number of concurrent users. This way you can adjust your load policy and eventually having some short peak.

Note that the number of users that you could have will be limited by your license.

 

For more information, see “Runtime” section in NeoLoad documentation.