Hi Everyone,
Please bare with me here as I'm a new to Neoload.
I'm looking for way to do a ramp up to 50 VU's within 1 minute starting with 1 VU.
Any suggestions?
Thank you,
Hi,
In Runtime/ Scenarios you need to use a 'Ramp-up' Load Variation policy. Change the time unit from the default (minutes) to second to be able to set the rampup profile.
Thanks christophe.
If I look at the runtime section, there is something that is called virtual users start.
If I choose sequentially, and fill-in 60 seconds, wouldn't that work exactly the same?
Will answered
christophe answered
Will posted a new question